Vent: my 3 ring binder schedule system died last year and I actually miss it
Ran my jobs off a giant 3 ring binder for about 9 years, printed schedule taped to the inside cover, change orders in the back pocket, daily logs in the middle. Then last March on a 14 unit townhome job in Boise I missed a submittal because a page got shuffled and we lost 3 days waiting on a door frame package. After that I moved everything to a shared spreadsheet and now my super pulls it up on his phone at 6am. It works, I won't lie, but I lose track of verbal promises now because nothing gets written on paper anymore. Last week a plumber swore he told me about a rough in conflict and I had no way to check. Anyone else find a middle ground where the crew actually updates it without me nagging them every Friday?