Can we talk about the two week look ahead meeting that finally fixed our Friday chaos?
For two years our Friday jobsite walk was a mess. Subs would show up with no idea what the next week looked like, and we were losing a full half day to people standing around asking each other what was next. Six months ago I started doing a 20 minute sit down every Thursday at 3pm with my three main foremen, and we write out the next two weeks on a whiteboard instead of just the current week. Last month we cut our framing crew's idle time by about 30 hours on the Cedar Ridge job alone. The trick was we don't talk about problems, only what work is coming and who owns it, then everyone leaves with a photo of the board on their phone. Two of the guys grumbled for the first month and now they're the ones asking if we can start the meeting early. Curious if anyone else runs a look ahead this short, or do you go further out?