Can we talk about the 7 weeks I spent getting one simple sign permit approved in Columbus?
I had a tenant lined up for a small retail spot on High Street and figured the sign permit would take maybe 10 days. It turned into 7 weeks because the city kicked it back three times, first for the dimensions, then for not having a drawing of the mounting bracket, then because the plan reviewer wanted the landlord's signature notarized. Every resubmit meant another 5 to 7 business days in the queue, and I lost the tenant to a spot two blocks away. Now I tell everyone to budget 4 to 6 weeks for signage alone. How long does it actually run in your city, and is there a way to get a pre-review before you file?