We were pulling up a piece of old pipeline off Galveston last fall, and the winch cable snapped at about 80 feet. The whole section dropped back down, stirred up a silt cloud you couldn't see through, and wrapped around the support legs of a nearby platform. It took our crew three extra days of careful cutting with hydraulic shears to free it without causing more damage. The client was not happy about the delay, but we avoided a much bigger problem. Has anyone else had a simple lift turn into a multi-day knot untying exercise?
2 comments
Log in to join the discussion
Log In2 Comments
the_lisa2d ago
Three extra days just to cut it free? That is a NIGHTMARE of a timeline. I would have lost my mind dealing with that client.